Read BOM and production costs

A BOM's cost view estimates what a recipe costs from your supplier prices. After a run, compare the order's actual quantities with that estimate.

Read a BOM's cost

  1. Open the output material in Materials and select BOM.
  2. Choose the version.
  3. Read Rolled-up Cost in the summary, and switch from Structure to Cost for the detail.
  4. Expand assemblies to see what each part contributes.

Rolled-up Cost adds up supplier prices for the quantities in the tree. Review labour, overhead and freight separately. For nested assemblies, an assembly and its sub-components can both show costs, so check the tree against your recipe.

For the Gift box in the BOM guide: if a kraft box is USD 1.00, tissue is USD 0.10 per sheet and ribbon is USD 0.30 per metre, one Gift box costs USD 1.50 in materials.

When you try alternatives with click to swap, the costs show Scenario until you save.

Add a supplier price to a component

  1. Select the component to open Component Detail.
  2. Select Add supplier and choose the Supplier.
  3. Check Supplier SKU, and enter Currency and Unit Cost if known.
  4. Tick Preferred supplier if this supplier should be used first.
  5. Select Add Supplier.

Check the result: the component shows the price, and Rolled-up Cost updates. To change prices later, edit them on the supplier's products. A price must be in the component's unit, so USD 24 per case of 24 is USD 1 each.

Missing or mixed costs

What you see Meaning
No cost data No usable prices for a total. Add supplier prices.
Withheld and Mixed currencies Prices are in more than one currency. Zapstra doesn't convert them, so no total is shown.
Cost Overlay Extra cost lines (such as overhead) recorded for the BOM, shown separately from Rolled-up Cost. If there are none, it says "No overhead items defined for this BOM."

Compare with a completed run

On a completed production order, compare each component's planned quantity, Actual qty and Excess, plus output and scrap. For the valuation of what was made, see cost layers and the inventory ledger.